Thames Water has appointed Barhale to deliver a programme of essential engineering works on the Beckton Sludge Main.

The civil engineering and infrastructure specialist will install a 1.8km single sludge rising main in 450mm pipe together with washout chambers and air valve chambers to replace a section of the 8km Beckton Sludge Main.

Once in place, Barhale will decommission the by-passed section of the original main and remove two pipe bridges that will become redundant.

Originally built between 1968 and 1970, the two pipelines of the Sludge Main carry wastewater sludge from Beckton Sewage Treatment Works (STW) in East London to Riverside STW for processing at the Thermal Hydrolysis Plant (THP) where it generates renewable energy.

The £6.4M design and build project will follow a new route along existing roads, diverting away from the original, less accessible, route which crossed a newly developed housing area in addition to rivers, ditches and ponds.

The all new pipe will be laid by open cut to a depth of two metres.

Nick Piggott, Business Opportunities, Proposals and Development Manager at Barhale explained that the Sludge Main was originally constructed to pump sludge from Riverside to Beckton where it was removed by ship.

“When the new sludge treatment works was installed at Beckton, the flows were reversed and the existing pipeline has delivered for more than 50 years,” he said. “However, time is catching up on the pipe and its condition has deteriorated.

“The installation of a new rising main, removing a 1.8km stretch of the original pipeline, will ensure reliable flows and strengthen the resilience of the network for many years to come.”

Thames Water’s Head of Programme Delivery – Waste London Infrastructure Jon Curry said:

“Thames Water is pleased to be working in collaboration with Barhale on this important waste project. Barhale has provided key input into planning and constructability to ensure customers continue to be served for years to come while minimising disruption to local stakeholders during the build process.”

SourceBarhale

NEWS CATEGORIES

LATEST NEWS

Steps to unlocking water data capability

The water sector has made good progress with digitisation – the capturing of data for storage and processing - writes Ruth Clarke, head of...

Steve Vick International’s innovative grout filling project for Wales & West Utilities in Aberdare

Steve Vick International's Contract Services team recently completed a challenging project in Aberdare, Wales, commissioned by Wales & West Utilities and Transport for Wales. ...

New AUMA actuators keep water in Welsh town’s taps flowing 

Water supplies to over 3,000 residents in the Welsh seaside town of Tywyn will continue to flow uninterrupted thanks to new state-of-the-art, remotely controlled...

New entry-level machine now available from Bucher Municipal

Bucher Municipal has announced a new addition to its sewer cleaner range. The new CityFlex C40 Viking unit provides an entry level product to...