January start for new phase of Exmoor supply boost

The final phase of a £850,000 improvement to water supply on the edge of Exmoor will get under way in January after project chiefs and the local community worked together to agree a plan to minimise its impact.

Wessex Water will complete their hefty investment to replace mains in and around Timberscombe from the start of 2025, having wrapped up the opening eight-month section of the work within the village earlier last year.

Teams will begin replacing pipes on the Clouds Steep and A396 Dunster to Timberscombe road to the north from January, in work that is expected to last for up to 16 weeks.

However, following consultation with the local parish council and listening to customers’ ideas at a community session back in September, the company will carry the work out at night, allowing one what is of the main A road routes through Exmoor to reopen to traffic during the day.

Wessex Water design engineer Egidijus Mockevicius said:

“Thanks to the patience of the local community and the hard work of our team, the opening phase of this project was completed earlier this autumn but, before starting the final part of it, it was important for us to speak again to local people about the best way to approach it.

“We’re grateful to the community, Timberscombe Parish Council and Somerset Council for playing a full part in these discussions and supporting our measures to try and keep disruption to a minimum wherever possible.

“Their guidance has been crucial to the planning of the project and we believe that carrying the work out at night allows us the best opportunity to finish it as promptly as possible.

“We’ll also be restricting the noisiest activity, such as road cutting or breaking to between 7-11pm, as well as using silent generators for lighting, while acoustic barriers will be placed around areas where pipe bursting and winching operations are taking place.’’

The utility company has also unveiled ambitious proposals in relation to the supply of water to ensure the system can cope with the growing demands from population growth and challenges of climate change, as part of £3.5 billion of new investment – within its 2025-2030 Business Plan.

NEWS CATEGORIES

LATEST NEWS

Severn Trent begins training new recruits in preparation for £415 million pipe renewal project

The first new recruits for Severn Trent’s multi-million pound project to install 870 miles of new water pipes have officially started.  The water company is...

South Staffordshire Plc appoints Joanna Smith as Group CFO following Rob O’Malley’s decision to step down

South Staffordshire Plc has appointed Joanna Smith as Group CFO, following Rob O’Malley’s decision to step down from the role in April 2025. Joanna Smith...

Welsh Government backs what will become the largest consented tidal energy project in Europe

The Welsh Government has taken an £8 million equity stake in the Morlais tidal scheme, which is set to become the largest consented tidal...

Graf appoints a commercial wastewater manager for Ireland and the UK

A wastewater specialist with 20 years of experience in the design, sales, installation and servicing of domestic, commercial and municipal systems has been appointed...