Key milestone for £3m green hydro energy scheme at East Lothian reservoir

Scottish Water has completed construction on a pioneering new type of hydro energy generation scheme at a reservoir in East Lothian, believed to be the first of its kind in Europe.

The £3million scheme, at Whiteadder Reservoir, is expected to offset almost a third of the energy used by one of East Lothian’s largest pumping stations, named Hungry Snout, which takes around 32 millions litres of water per day to Castle Moffat Water Treatment Works before it goes on to supply most of the East Lothian region with drinking water.

The project allows green energy to be generated whilst also accurately controlling the level of the reservoir during seasonal fluctuations in weather.

Through the use of siphon technology, water is drawn up through the intake and over the top of the dam before running down through the siphon, through the hydro turbine, and back to the natural environment.

The project has been led by Scottish Water Horizons, the public utility’s commercial subsidiary, and delivered by renewable energy specialists Emtec Energy.

The new hydro turbine at Whiteadder Reservoir will meet 30% of the energy needed to power the Hungry Snout pumping station - one of the biggest in East Lothian.
The new hydro turbine at Whiteadder Reservoir will meet 30% of the energy needed to power the Hungry Snout pumping station – one of the biggest in East Lothian.

Acting Net Zero and Energy Secretary Gillian Martin said:

“This is a very welcome milestone in green energy and Scotland’s goal to reach net zero emissions by 2045. Scottish Water’s £3 million investment in this innovative technology, the first of its kind in Europe, is maximising the value of our water resources, reducing emissions and delivering benefits to customers by reducing costs which can be re-invested.

“Further investment in innovative technology will be required to adapt to the challenges presented by climate change, ensuring our water supply is more resilient and our waterways cleaner.”

Senior Project Manager at Scottish Water Horizons, Neil Beaumont, said:

“We are delighted to have completed construction of this exciting project which will produce enough green energy to meet 30% of the power needs of the Hungry Snout pumping station and reduce our reliance on drawing energy from the national grid.

“We also wanted to ensure our carbon footprint was as low as possible throughout the construction process, which is why we used divers and barges to sink the pipes under the water – this was a much less intrusive and carbon intensive way of installing the new infrastructure than more traditional methods.”

He added: “The scheme will ensure that we are protecting the water levels of the reservoir via smart controls and sensors, so that we are never taking too much water in order to power the hydro turbine – the reservoir’s primary function is to provide water to customers.”

The new scheme will see water siphoned up over the top of the dam before running down through the siphon through the hydro turbine and back to the natural environment.
The new scheme will see water siphoned up over the top of the dam before running down through the siphon through the hydro turbine and back to the natural environment.

The investment at Whiteadder will significantly reduce the carbon emissions from the pumping station, saving approximately 111 tonnes of carbon each year, the equivalent of a passenger jet flying from Edinburgh to Sydney, Australia 40 times.

It is expected to generate 0.82GWh of renewable energy per annum from the 199kW turbine.

Scottish Water’s General Manager for Net Zero, Elise Cartmell, said:

“Scottish Water is always looking for opportunities to create renewable energy via our assets, and this scheme joins over 30 hydro turbines already installed at our sites around the country.

“In the coming year, this number is set to increase as work starts on further hydro power schemes – we are proud to be leading the sector with innovative projects such as these which lower the carbon footprint of the local water supply.

“As a business, we are fully committed to meeting our ambitious net zero emission targets, and will continue to ramp up our production of green energy as quickly as we can.”

Scottish Water has committed to meeting net zero total emissions across all its operational and investment activities by 2040.

NEWS CATEGORIES

LATEST NEWS

WaterEquity announces $100M in financing available for water and sanitation infrastructure

WaterEquity, a global asset manager dedicated to mobilizing private investment for the water and sanitation sector, has raised more than $100 million for its...

Binnies awarded place on United Utilities’ network modelling framework for AMP8

Binnies, a leading water and environmental engineering whole life cycle services provider, has been awarded a position on United Utilities’ AMP8 network modelling framework....

Humber defences project reaches new milestone

The Environment Agency’s £29m Stallingborough 3 sea defence improvements project between Immingham and Grimsby has reached a significant milestone. 90,000 tonnes of rock amour protecting...

Ballyronan to benefit from new £5m Wastewater Treatment Works

NI Water has announced the completion of a £5m programme of work to provide Ballyronan with a modern new wastewater treatment facility. The existing treatment...