QEII reservoir back in action and refilled with equivalent of 8,000 Olympic pools of water

A £25 million investment project to help protect London’s water supply for the next decade has been successfully completed ahead of schedule in Walton-on-Thames.

Work to drain the Queen Elizabeth II reservoir, which stores around ten per cent of all of London’s pre-treated drinking water, began in April 2021 so that essential maintenance could be carried out to help protect the capital’s water supply. The reservoir was not due to be refilled until this summer, but after maintenance work finished ahead of schedule, the reservoir has been gradually filling up since November. From March 1st has officially returned to servicing and supplying water to the nearby Hampton water treatment works.

The reservoir is one of the largest in the region and when full holds 19,623 million litres of water – the equivalent of around 8,000 Olympic swimming pools.

While it was drained engineers relined the two tunnels which feed water into the reservoir from the River Thames and carries it from there to the nearby treatment works, from where it is pumped to homes across London. The relining has strengthened the tunnels to prevent any future leaks.

Rachel Whiteman, Thames Water’s project manager, said: “The QEII plays a really important role in the supply of top-quality drinking water for millions of people across Surrey and London, so we’re delighted we’ve been able to carry out the vital maintenance work and refill it ahead of schedule. It’s been a huge effort by the whole team and we’d like to thank everyone in the area for their patience while we temporarily had a road closed and had construction vehicles coming on and off the site.”

NEWS CATEGORIES

LATEST NEWS

EPA announces funding of €6.6million for new research that will address environmental, climate and sustainability challenges in Ireland

The Environmental Protection Agency (EPA) has announced funding of €6.6million for targeted new research projects to address environmental, climate and sustainability challenges in Ireland. The...

DAERA Minister Andrew Muir responds to OEP report on improving protection for nature in Northern Ireland

Northern Ireland's Department of Agriculture, Environment and Rural Affairs (DAERA) Minister Andrew Muir has committed to ensuring that full and prompt consideration is given...

Portsmouth Water begins its biggest environmental study ever on river catchments

Portsmouth Water has initiated a £4 million comprehensive environmental study to assess and implement actions necessary to ensure the sustainability of future water abstraction. The...

Zelim-sponsored pacific row to raise funds for clean water

Setting out in April from Lima, Peru, three Scottish siblings aim to row non-stop and unsupported across the Pacific Ocean in a potentially record-breaking...