QEII reservoir back in action and refilled with equivalent of 8,000 Olympic pools of water

A £25 million investment project to help protect London’s water supply for the next decade has been successfully completed ahead of schedule in Walton-on-Thames.

Work to drain the Queen Elizabeth II reservoir, which stores around ten per cent of all of London’s pre-treated drinking water, began in April 2021 so that essential maintenance could be carried out to help protect the capital’s water supply. The reservoir was not due to be refilled until this summer, but after maintenance work finished ahead of schedule, the reservoir has been gradually filling up since November. From March 1st has officially returned to servicing and supplying water to the nearby Hampton water treatment works.

The reservoir is one of the largest in the region and when full holds 19,623 million litres of water – the equivalent of around 8,000 Olympic swimming pools.

While it was drained engineers relined the two tunnels which feed water into the reservoir from the River Thames and carries it from there to the nearby treatment works, from where it is pumped to homes across London. The relining has strengthened the tunnels to prevent any future leaks.

Rachel Whiteman, Thames Water’s project manager, said: “The QEII plays a really important role in the supply of top-quality drinking water for millions of people across Surrey and London, so we’re delighted we’ve been able to carry out the vital maintenance work and refill it ahead of schedule. It’s been a huge effort by the whole team and we’d like to thank everyone in the area for their patience while we temporarily had a road closed and had construction vehicles coming on and off the site.”

NEWS CATEGORIES

LATEST NEWS

The Chief Scientist’s Group says we need to change the way we think about the value and benefits of clean and plentiful water

In the Chief Scientist's Annual Review 2024, the Chief Scientist's Group has said we need to change the way we think about the value...

New trade association unveiled for the property flood resilience sector

A new trade body has been formed to represent and professionalise the rapidly growing property flood resilience (PFR) industry. The International Property Flood Resilience Association...

South East Water collaborates with Future Nature to Champion regenerative agriculture

Local land owners, farms, businesses and students are invited to attend an informative workshop focusing on regenerative farming at Hyde Farm, Maidenhead on 13...

Cutting-edge strategy puts Burntwood Sewage Treatment Works ahead of schedule

Expansion works at the Burntwood Sewage Treatment Works are expected to complete ahead of time, with two additional treatment stages constructed. Severn Trent Water contracted...